Site Preparation Checklist for EX4650 Switches

The checklist in Table 1 summarizes the tasks you need to perform to prepare a site for installing an EX4650 switch.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed by

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed switch tolerances.

Environmental Requirements and Specifications for EX Series Switches

   
Power

Measure the distance between external power sources and the switch installation site.

     

Locate sites to connect system grounding.

     

Calculate the power consumption and requirements.

EX4650 Power System

   
Hardware Configuration

Choose the number and types of switches you want to install.

EX4650 Switches Hardware Overview

   
Rack or Cabinet

Verify that the rack meets the minimum requirements for installing the switch.

   

Plan rack or cabinet location, including required space clearances.

     

Secure the rack or cabinet to the floor and building structure.

     
Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of the cable based on the distance between the hardware components being connected.

     

Plan the cable routing and management.