The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for a QFX5130-32CD installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed By

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed switch tolerances.

QFX5130-32CD Site Guidelines and Requirements

 

 

Power

Measure the distance between external power sources and switch installation site.

 

 

Calculate the power consumption and requirements.

QFX5130-32CD Power System

 

 

Rack or Cabinet

Verify that your rack or cabinet meets the minimum requirements for the installation of the switch.

 

 

Plan rack or cabinet location, including required space clearances.

QFX5130-32CD Clearance Requirements for Airflow and Hardware Maintenance

 

 

Secure the rack or cabinet to the floor and building structure.

 

 

Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

Determining QFX5130-32CD Optical Interface Support

 

 

Plan the cable routing and management.