Site Preparation Checklist for ACX7509 Routers

The following checklist summarizes the tasks you need to perform when preparing a site for an ACX7509 router installation. It provides blank spaces for entering the name of the person who performs each task and the date the task is completed.

Table 1: Site Preparation Checklist for ACX7509 Routers

Item or Task

For More Information

Performed By

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed router tolerances.

Environmental Requirements and Specifications for ACX7509 Routers

 

 

Power

Measure the distance between external power sources and the router installation site.

 

 

 

Calculate the power consumption and requirements.

ACX7509 Power System

 

 

Rack or Cabinet

Verify that your rack or cabinet meets the minimum requirements for router installation.

ACX7509 Rack and Cabinet Requirements

 

 

Plan rack or cabinet location, including required space clearances.

Clearance Requirements for Airflow and Hardware Maintenance of ACX7509 Routers

 

 

Secure the rack or cabinet to the floor and building structure.

 

 

 

Cables

Acquire cables and connectors:

  • Determine the number of cables needed for your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

 

 

 

Plan cable routing and management.