Site Preparation Checklist for ACX7509 Routers
The following checklist summarizes the tasks you need to perform when preparing a site for an ACX7509 router installation. It provides blank spaces for entering the name of the person who performs each task and the date the task is completed.
Item or Task |
For More Information |
Performed By |
Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed router tolerances. |
Environmental Requirements and Specifications for ACX7509 Routers |
|
|
Power | |||
Measure the distance between external power sources and the router installation site. |
|
|
|
Calculate the power consumption and requirements. |
|
|
|
Rack or Cabinet | |||
Verify that your rack or cabinet meets the minimum requirements for router installation. |
|
|
|
Plan rack or cabinet location, including required space clearances. |
Clearance Requirements for Airflow and Hardware Maintenance of ACX7509 Routers |
|
|
Secure the rack or cabinet to the floor and building structure. |
|
|
|
Cables | |||
Acquire cables and connectors:
|
|
|
|
Plan cable routing and management. |
|
|