Add Link per Superspine (5-Stage)

As a Day 2 operation, you can add links per superspine on 5-stage blueprints (as of Apstra version 4.1.0).
  1. From the blueprint, navigate to Staged > Physical > Pods.
  2. Click the Update spine config button. The location of the button is different for different Apstra versions.
    • On Apstra version 4.1.2, click the Update spine config button on the bottom-right of the card for the pod to change

    • On Apstra versions 4.1.1 and 4.1.0, check the box on the top-left of the card for the pod to change. Then click the Update spine config button that appears above the card(s).

  3. In the Link per superspine field, enter the total number of links you want between spines and superspines. You can only add links. Plan carefully. After you add links, you won't be able to remove them later.
  4. Click Update to stage your changes and return to the Pods view.

When you're ready to activate changes, commit them from the Uncommitted tab.