Site Preparation Checklist for the SRX5600 Firewall

The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for firewall installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information ...

Performed By

Date

Verify that environmental factors such as temperature and humidity do not exceed firewall tolerances.

SRX5600 Firewall Environmental Specifications

   

Select the type of rack or cabinet.

SRX5600 Firewall Cabinet Size and Clearance Requirements,SRX5600 Firewall Rack Size and Strength Requirements

   

Plan rack or cabinet location, including required space clearances.

Clearance Requirements for SRX5600 Firewall Airflow and Hardware Maintenance

   

If a rack is used, secure rack to floor and building structure.

Connection to Building Structure for the SRX5600 Firewall Rack

   

Acquire cables and connectors.

     

Locate sites for connection of system grounding.

DC Power Electrical Safety Guidelines and Warnings

   

Measure distance between external power sources and firewall installation site.

     

Calculate the optical power budget and optical power margin.

Calculating Power Budget for Fiber-Optic Cable for the SRX5600 Firewall,Calculating Power Margin for Fiber-Optic Cable for the SRX5600 Firewall