SRX4200 Site Preparation Checklist

Table 1 provides a checklist of tasks you need to perform when preparing a site for installing the SRX4200 Services Gateway.

Table 1: Site Preparation Checklist for SRX4200 Services Gateway Installation

Item or Task

Additional Information

Performed By

Date

Notes

Power

Measure distance between external power sources and device installation site.

 

Locate sites for connection of system grounding.

 

Calculate the power consumption and requirements.

AC Power Supply Specifications for SRX4200 Services Gateways

DC Power Supply Specifications for SRX4200 Services Gateways

Environment

Verify that environmental factors such as temperature and humidity do not exceed device tolerances.

SRX4200 Services Gateway Environmental Specifications

Rack or Cabinet

Verify that your rack or cabinet meets the minimum requirements for the installation of the device.

SRX4200 Services Gateway Rack Requirements

Cabinet Requirements for SRX4200 Services Gateways

Plan rack location, including required space clearances.

Secure the rack or cabinet to the floor and building structure.

Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

Plan the cable routing and management.