Help us improve your experience.

Let us know what you think.

Do you have time for a two-minute survey?

 
 

Site Preparation Checklist for a QFX3600 or QFX3600-I Device

The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for QFX3600 or QFX3600-I device installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed By

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed device tolerances.

Environmental Requirements and Specifications for QFX3600 and QFX3600-I Devices

 

 

Power

Measure distance between external power sources and device installation site.

 

 

 

Calculate the power consumption and requirements.

AC Power Specifications for a QFX3600 or QFX3600-I Device

DC Power Specifications for a QFX3600 or QFX3600-I Device

 

 

Rack or Cabinet

Verify that your rack or cabinet meets the minimum requirements for the installation of the switch.

Rack Requirements for a QFX3600 or QFX3600-I Device

Cabinet Requirements for a QFX3600 or QFX3600-I Device

 

 

Plan rack or cabinet location, including required space clearances.

Clearance Requirements for Airflow and Hardware Maintenance for a QFX3600 or QFX3600-I Device

 

 

Secure the rack or cabinet to the floor and building structure.

 

 

 

Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

Determining Interface Support for the QFX3600 Device

Determining Transceiver Support for QFabric Systems

 

 

Plan the cable routing and management.