Site Preparation Checklist for NFX350 Devices

The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for NFX350 devices installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed by

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed device tolerances.

NFX350 Site Guidelines and Requirements

   
Power

Measure distance between external power sources and device installation site.

     

Locate sites for connection of system grounding.

     

Calculate the power consumption and requirements.

NFX350 Power System

   
Hardware Configuration

Choose the number and types of devices you want to install.

NFX350 Network Services Platform Overview

   
Rack or Cabinet

Verify that your rack or cabinet meets the minimum requirements for the installation of the device.

Rack Requirements for NFX350 Devices

Cabinet Requirements for an NFX350 Device

   

Plan rack or cabinet location, including required space clearances.

Clearance Requirements for Airflow and Hardware Maintenance for an NFX350 Device

   

Secure the rack or cabinet to the floor and building structure.

     
Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

     

Plan the cable routing and management.