Help us improve your experience.

Let us know what you think.

Do you have time for a two-minute survey?

 
 

ACX6360 Site Preparation Checklist

The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for an ACX6360 installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed by

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed router tolerances.

ACX6360 Environmental Requirements and Specifications

 

 

Power

Measure the distance between external power sources and the router installation site.

 

 

 

Calculate the power consumption and requirements.

 

 

Rack or Cabinet

Verify that your rack or cabinet meets the minimum requirements for the installation of the router.

 

 

Plan rack or cabinet location, including required space clearances.

Figure 1

 

 

Secure the rack or cabinet to the floor and building structure.

 

 

 

Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.

  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

 

 

Plan the cable routing and management.