Site Preparation Checklist for EX-series Switches
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for switch installation.
Table 1: Site Preparation Checklist
Item or Task |
For More Information |
Performed By |
Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances. | |||
Power | |||
Measure distance between external power sources and switch installation site. | |||
Locate sites for connection of system grounding. | |||
Calculate the power consumption and requirements. |
Power Specifications and Requirements for an EX-series Switch | ||
Hardware Configuration | |||
Choose the number and types of switches you want to install. | |||
Rack or Cabinet | |||
Verify that your rack meets the minimum requirements for the installation of the switch. |
Rack Requirements and Specifications for an EX-series Switch Cabinet Requirements and Specifications for an EX-series Switch | ||
Plan rack location, including required space clearances. | |||
Secure the rack to the floor and building structure. | |||
Cables | |||
Acquire cables and connectors:
| |||
Plan the cable routing and management. |