Unpacking and Mounting the EX6210 Switch

 

Unpacking an EX6200 Switch

After you prepare the installation site as described in Site Preparation Checklist for an EX6210 Switch, you may unpack the switch.

Note

The switch is maximally protected inside the shipping box. Do not unpack it until you are ready to begin installation.

Ensure that you have the following parts and tools available to unpack the EX6200 switch:

  • A 7/16-in. or 11-mm open-end or socket wrench to remove the nuts from the bracket bolts (the side of the attached to the chassis).

  • A 10-mm open-end or socket wrench to remove the nuts from the bracket bolts (the side of the attached to the shipping pallet).

  • A box cutter or packing knife to slice open the tape that seals the top of the box

The switch ships in a cardboard box that has a two-layer wooden pallet base with foam cushioning between the layers. The switch chassis is bolted to the pallet base.

The EX6210 chassis ships with one Switch Fabric and Routing Engine (SRE) module, fan tray, an AC or DC power supply, and two line cards for the configuration you ordered already installed. Any additional SRE modules, line cards, or power supplies ordered ship separately. See EX6210 Switch Configurations for information about different shipping configurations.

To unpack the switch (see Figure 2):

  1. Move the shipping box to a staging area as close to the installation site as possible. For the switch, make sure there is enough space to remove components from the chassis if necessary (for example, if you do not have a mechanical lift to use when you install the switch). While the chassis is bolted to the pallet, you can use a forklift or pallet jack to move it.
  2. Position the shipping box with the arrows pointing up.
  3. Open the four pallet fasteners near the bottom of the shipping box that attach the cardboard box to the wooden pallet. To open a pallet fastener, squeeze together the two ridges (“fins”) in the depression in the latch, then slide the pallet fastener out of the cardboard box slot in which it is inserted. See Figure 1.
    Figure 1: Pallet Fastener
    Pallet Fastener
  4. Carefully slice open the tape that holds the top of the cardboard box closed and open the top of the box.
  5. Remove the cardboard accessory box from the center of the foam padding.
  6. Remove the foam padding from the top of the box.
  7. Slide the cardboard box off the pallet.
  8. Remove the plastic cover from the switch chassis.
  9. Use a 7/16-in. or 11-mm open-end or socket wrench to remove the four sets of bracket bolts that secure the chassis to the shipping pallet (on the chassis side).
  10. Use a 10-mm open-end or socket wrench to remove the four sets of bracket bolts that secure the chassis to the shipping pallet (on the pallet side).
  11. Unpack the accessory box and lay out the contents so that they are ready for use.
  12. Verify that your order includes all appropriate parts. See Parts Inventory (Packing List) for an EX6210 Switch .
  13. Store the brackets and bolts inside the accessory box.
  14. Save the shipping box, pallet, and packing materials in case you need to move or ship the switch at a later time.
Figure 2: Unpacking an EX6210 Switch
 Unpacking an EX6210 Switch

Unpacking an EX6200 Line Card

The line cards for EX6200 switches are rigid sheet-metal structures that house the line card components including network ports. The line cards are shipped in a cardboard carton, secured with foam packing material.

Caution

The line cards are maximally protected inside the shipping carton. Do not unpack the line cards until you are ready to install them in the switch chassis.

Before you unpack a line card:

To unpack a line card (see Figure 3):

  1. Move the shipping carton to a staging area as close to the installation site as possible.
  2. Position the carton so that the arrows are pointing up.
  3. Open the top flaps on the shipping carton.
  4. Pull out the packing material, which holds the line card in place.
  5. Remove the line card from the antistatic bag.
  6. Save the shipping carton and packing materials in case you need to move or ship the line card later.
Figure 3: Unpacking a Line Card Used in an EX6200 Switch
Unpacking a Line Card Used in an EX6200 Switch

Parts Inventory (Packing List) for an EX6210 Switch

Check the parts you receive in the switch shipping crate against the items on the packing list or customer information sheet. (The remainder of this topic uses packing list to mean packing list or customer information sheet.) The packing list specifies the part number and description of each part in your order. The parts shipped depend on the configuration you order. See EX6210 Switch Configurations for more information.

If any part on the packing list is missing, contact your customer service representative or contact Juniper customer care from within the U.S. or Canada by telephone at 1-888-314-5822. For international-dial or direct-dial options in countries without toll-free numbers, see https://www.juniper.net/support/requesting-support.html.

Note

Additional line cards and power supplies ordered are shipped separately.

Table 1 lists the parts and their quantities in the packing list for the shipping configurations of the EX6210 switch.

Table 1: Parts List for Different EX6210 Switch Configurations

Component

Shipping Configuration Quantity

Chassis, including the backplane and front-mounting brackets

1

Switch Fabric and Routing Engine (SRE) module

1

Line cards

One of the following:

  • Two 48-port RJ-45 line cards

  • Two 48-port PoE+ line cards

Power supplies

One of the following:

  • One 2500 W AC power supply

  • One 5000 W AC power supply

  • One 2100 W DC power supply

Power supply cords

For AC systems only:

  • 1 per 2500 W AC power supply or 2 per 5000 W AC power supply

Fan tray

1

Cover panels for slots without installed components

  • Line card cover panels: 6

  • SRE module cover panel: 1

    Note: The SRE module cover panel consists of 1 line card cover panel and 1 SRE module filler panel.

  • One of the following:

    • Three 2500 W AC power supply cover panels

    • Three 5000 W AC power supply cover panels

    • Three 2100 W DC power supply cover panels

Power supply blank shelf

For all systems that ship with 2500 W AC or 2100 W DC power supplies:

  • 1

Note: The power supply blank shelf is not included with systems that ship with 5000 W AC power supplies.

Table 2 lists the parts contained in the accessory box.

Table 2: Accessory Box Parts List

Component

Quantity

Label, accessories contents

1

Documentation Roadmap

1

Power cord retainers

For AC systems only:

  • 1 per 2500 W AC power supply or 2 per 5000 W AC power supply

Juniper Networks Product Warranty

1

End User License Agreement

1

Juniper Compliance Form Letter, RoHS Worldwide

1

Ethernet cable, RJ-45/RJ-45, 4-pair stranded UTP, category 5E

1

RJ-45 to socket DB-9 cable, to connect to the switch's console port using a management PC's serial port

1

ESD grounding strap

1

DC terminal lug (Panduit LCD4-14A-L)

For DC systems only:

  • 2

Chassis grounding kit

  • Grounding lug (Panduit LCD2-14A-Q):1

  • Screws (1/4-20 x 0.5 in.): 2

  • Flat washers: 2

Note

You must provide mounting screws that are appropriate for your rack or cabinet to front-mount the chassis on a rack or a cabinet.

The EX6200-48F line cards are not part of the shipment; you must order them separately.

For two-post rack installation, you need either 24 or 28 screws: 24 screws to attach the front-mounting bracket ears that come installed on the chassis to the front of the rack and 4 screws if you install the optional power cord tray.

For four-post rack installation, you need either 40 or 44 screws: 24 screws to attach the front-mounting bracket earsthat come installed on the chassis to the front of the rack, 16 screws to attach the adjustable mounting brackets to the rack, and 4 screws if you install the optional power cord tray.

Installing and Connecting an EX6210 Switch

The EX6210 switch chassis is a rigid sheet-metal structure that houses the other hardware components such as Switch Fabric and Routing Engine (SRE) modules, AC or DC power supplies, a fan tray, and line cards. The switch ships in a cardboard box that has a two-layer wooden pallet base. The switch chassis is bolted to the pallet base.

To unpack an EX6210 switch, follow instructions in Unpacking an EX6200 Switch.

You can install an EX6210 switch in a 19-in. rack or cabinet by using the front-mounting bracket attached to the chassis. To install the switch in a rack or cabinet, follow the instructions in Mounting an EX6210 Switch on a Rack or Cabinet Using a Mechanical Lift or Mounting an EX6210 Switch on a Rack or Cabinet Without Using a Mechanical Lift.

To connect an EX6210 switch to earth ground, follow instructions in Connect Earth Ground to an EX Series Switch.

To connect power to the switch chassis, follow instructions in Connecting AC Power to an EX6200 Switch or Connecting DC Power to an EX6200 Switch.

To connect and configure the switch, follow instructions in Connecting and Configuring an EX Series Switch (CLI Procedure).



To connect the switch to a network for out-of-band management, follow instructions in Connect a Device to a Network for Out-of-Band Management. To connect the switch to a management console, follow instructions in Connect a Device to a Management Console Using an RJ-45 Connector.

Installing Adjustable Mounting Brackets in a Rack or Cabinet for an EX6200 Switch

Note

The adjustable mounting brackets are optional for four-post rack and cabinet installations of EX6200 switches.

The adjustable mounting brackets do not ship with the EX6200 switches. You can purchase them separately.

To mount the switch on a four-post rack or cabinet, you can install the optional adjustable mounting brackets in the rack or cabinet. (The remainder of this topic uses “rack” to mean “rack or cabinet.”) The four-piece set of adjustable mounting brackets support the EX6200 chassis in a four-post rack.

Note

The adjustable mounting brackets are not for installation in two-post racks.

The four adjustable mounting bracket pieces are:

  • 1 left front adjustable mounting bracket. The bracket is labeled “LEFT FRONT” on the side of the bracket that faces the interior of the rack, near the holes for attaching the bracket to the rack.

  • 1 right front adjustable mounting bracket. The bracket is labeled “RIGHT FRONT” on the side of the bracket that faces the interior of the rack, near the holes for attaching the bracket to the rack.

  • 2 rear adjustable mounting brackets. These brackets are labeled “REAR” on the side of the bracket that faces the interior of the rack, near the holes for attaching the bracket to the rack. The rear brackets are interchangeable; you can use either of the rear brackets with the right or left front adjustable mounting bracket.

Ensure that you have the following parts and tools available to install the adjustable mounting brackets:

  • A Phillips (+) screwdriver, number 1, 2, or 3, depending on the size of your rack mounting screws

  • A Phillips (+) screwdriver, number 2 to install the screws that connect the rear and front mounting brackets

  • 16 mounting screws appropriate for your rack to attach the four mounting bracket pieces to the rack

When you install the adjustable mounting brackets, the “arms” of the brackets overlap. The overlap area adjusts the total bracket length to fit three standard rack sizes: 23.62 in. (600 mm), 30 in. (762 mm), and 31.5 in. (800 mm).

To install the mounting brackets in a four-post rack (see Figure 5):

  1. Remove the adjustable mounting brackets from the box.
  2. Decide where to position the switch in the rack. If the rack is empty, position the switch in the lowest possible location. See Rack Requirements, and Cabinet Requirements.
  3. Position the left front adjustable mounting bracket at the desired position in the left side of the rack and line up its front screw holes with the holes in the rack. Use 4 mounting screws appropriate for your rack to attach the left front bracket to the rack.
  4. Position one of the rear brackets at the left rear of the rack on the same level as the left front bracket, so that the rear bracket overlaps with the left front bracket. The screw holes for connecting the front and rear brackets should overlap. Use 4 mounting screws appropriate for your rack to attach the rear bracket to the rack.
  5. Connect left front and rear brackets (see Figure 4):
    1. Insert 6 of the screws provided with the mounting brackets into the overlapping bracket holes.
    2. Tighten the screws fully (to 12–16 in.-lb torque) using a number 2 Phillips screwdriver.
    Figure 4: Adjustable Mounting Brackets for Four-Post Rack Installation
    Adjustable Mounting
Brackets for Four-Post Rack Installation
  6. Position the right front adjustable mounting bracket at the desired position in the right side of the rack opposite the installed left front bracket, so that it is on the same rack level as the left bracket. If the right and left front brackets are not on the same level, the chassis will rest at an angle in the rack instead of resting flat and level. Line up the right bracket's front screw holes with the holes in the rack. Use 4 mounting screws appropriate for your rack to attach the right front bracket to the rack.
  7. Position the other rear bracket at the right rear of the rack on the same level as the right front bracket, so that the rear bracket overlaps with the right front bracket. The screw holes for connecting the front and rear brackets should overlap. Use 4 mounting screws appropriate for your rack to attach the rear bracket to the rack.
  8. Connect the right front and rear brackets (see Figure 4):
    1. Insert 6 of the screws provided with the mounting brackets into the overlapping bracket holes.
    2. Tighten the screws fully (to 12–16 in.-lb torque) using a number 2 Phillips screwdriver.
Figure 5: Adjustable Mounting Brackets Installed in a Four-Post Rack (EX6210 Switch)
Adjustable
Mounting Brackets Installed in a Four-Post Rack (EX6210 Switch)

Installing the Power Cord Tray in a Rack or Cabinet for an EX6200 Switch

Note

The power cord tray is optional for four-post and two-post rack or cabinet installations of EX6200 switches.

The power cord tray does not ship with the EX6200 switches. You can purchase it separately.

The power cord tray provides a place to organize and tie down the power cords for the power supplies. It also provides support for the front of the EX6210 chassis during installation of the switch in a two-post rack. The front edge of the chassis rests on the upper edge (lip) of the power cord tray.

The power cord tray uses 1 U of rack space (the remainder of this topic uses “rack” to mean “rack or cabinet” ) , so the total space occupied by an EX6210 switch chassis and power cord tray is 15 U.

Ensure that you have the following tools and parts available to install the power cord tray:

  • A Phillips (+) screwdriver, number 1, 2, or 3, depending on the size of your rack mounting screws

  • 4 mounting screws appropriate for your rack to attach the power cord tray to the rack

To install the power cord tray (see Figure 6 and Figure 7):

  1. Remove the power cord tray from the shipping box.
  2. Decide where to position the switch in the rack. If the rack is empty, choose the lowest possible location. See Rack Requirements, and Cabinet Requirements.
  3. Position the power cord tray in the rack space immediately below the position in which you want to install the switch or where the switch is installed (see Figure 6). Line up the screw holes of the power cord tray with the holes in the rack. Use 4 mounting screws appropriate for your rack to attach the power cord tray to the rack.
Figure 6: Installing the Power Cord Tray in a Four-Post Rack
Installing the Power
Cord Tray in a Four-Post Rack
Figure 7: Power Cord Tray Installed in a Two-Post Rack
 Power Cord Tray
Installed in a Two-Post Rack

Mounting an EX6210 Switch on a Rack or Cabinet

The EX6210 switch ships installed with front-mounting brackets on the chassis for mounting the switch on a 19-in. rack or cabinet. You can purchase the optional adjustable mounting brackets to support the switch in a four-post rack and the optional power cord tray to manage the power supply cords.

In the rack, the switch consumes 14 U without the optional power cord tray and 15 U with the optional power cord tray. You can mount up to three switches on a 42 U rack or on a 45 U rack provided that the racks meet the strength requirements to support the combined weight of the switches.

Note

If you are mounting multiple switches on a rack or cabinet, mount a switch on the bottom of the rack or cabinet first and then mount the rest of the switches from bottom to top.

Warning

If you install the switch without using a mechanical lift, at least two people must be available to lift the unloaded switch chassis (all components except the backplane removed).

Before mounting the switch on a rack or cabinet:

Ensure that you have the following parts and tools available to mount the switch on a rack or cabinet:

  • A Phillips (+) screwdriver, number 2 or number 3, depending on the size of your rack mounting screws, for mounting the switch on a rack or cabinet

  • A Phillips (+) screwdriver, number 2, to remove the power supply from the chassis if you are mounting the switch without using a mechanical lift

  • 24 mounting screws appropriate for your rack

To mount the switch on a rack or cabinet (see Figure 8 and Figure 9):

  1. In a four-post rack or cabinet, you can install the optional adjustable mounting brackets at the desired position (see Installing Adjustable Mounting Brackets in a Rack or Cabinet for an EX6200 Switch).

    In a two-post rack or cabinet, you can install the optional power cord tray (see Installing the Power Cord Tray in a Rack or Cabinet for an EX6200 Switch).

  2. Lift the chassis into the rack using a mechanical lift. For instructions on how to install the chassis using a mechanical lift, see Mounting an EX6210 Switch on a Rack or Cabinet Using a Mechanical Lift.

    In a four-post rack, you can place the chassis on the adjustable mounting brackets, if installed, or align the front-mounting bracket holes with the rack rail holes with at least one person supporting the rear of the chassis until you can bolt the chassis into the rack.

    In a two-post rack, you can place the front edge of the chassis on the lip of the power cord tray, if installed, or align the front-mounting bracket holes with the rack rail holes with at least one person supporting the rear of the chassis until you can bolt the chassis into the rack.

    If a mechanical lift is not available, remove all components and ensure that at least two people are available to lift the empty chassis into the rack. For instructions on how to install the chassis without using a mechanical lift, see Mounting an EX6210 Switch on a Rack or Cabinet Without Using a Mechanical Lift.

  3. Insert 24 mounting screws appropriate for your rack (not provided) into the aligned holes. Use the appropriate Phillips (+) screwdriver to tighten the screws to the rack or cabinet rail.
Figure 8: Installing an EX6210 Switch in a Two-Post Rack
Installing an EX6210
Switch in a Two-Post Rack




Figure 9: Installing an EX6210 Switch in a Four-Post Rack
Installing an EX6210
Switch in a Four-Post Rack

Mounting an EX6210 Switch on a Rack or Cabinet Using a Mechanical Lift

You can use a mechanical lift to install the EX6210 switch.

Note

For instructions on installing a switch without using a mechanical lift, see Mounting an EX6210 Switch on a Rack or Cabinet Without Using a Mechanical Lift.

Caution

Before front-mounting the switch on a rack or cabinet, have a qualified technician verify that the rack or cabinet is strong enough to support the switch's weight and is adequately supported at the installation site.

Before you install the switch:

Ensure that you have the following parts and tools available to install the switch:

  • A mechanical lift

  • 24 mounting screws appropriate for your rack

  • A Phillips (+) screwdriver, number 2 or number 3, depending on the size of your rack mounting screws

Caution

If you are installing more than one switch in a rack or cabinet, install the first switch at the bottom of the rack.

To install the switch using a mechanical lift (see Figure 10):

  1. Ensure that the rack or cabinet is placed in its permanent location and is secured to the building. Ensure that the installation site allows adequate clearance for both airflow and maintenance. For details, see Clearance Requirements for Airflow and Hardware Maintenance for an EX6210 Switch.
  2. Load the switch onto the lift, making sure it rests securely on the lift platform.
    Figure 10: Installing the EX6210 Switch Chassis Using a Mechanical Lift
    Installing the EX6210
Switch Chassis Using a Mechanical Lift
  3. Using the lift, position the switch in front of the rack or cabinet, centering it in front of the rails of the rack or cabinet or the adjustable mounting brackets and/or power cord tray, if installed.
  4. Lift the chassis approximately 0.75 in. (1.9 cm) above the surface of the adjustable mounting brackets/power cord tray, if installed. Position the chassis in the rack as close as possible to resting on the support that the mounting brackets and/or power cord tray provide.
  5. In the rack, carefully slide the switch into the rack until the front-mounting brackets attached to the chassis contact the rack rails. The front-mounting brackets (ears) prevent the chassis from tipping too far back. Ensure that at least one person is supporting the rear of the chassis.

    In a four-post rack, carefully slide the switch onto the adjustable mounting brackets, if installed, until the front-mounting brackets (ears) attached to the chassis contact the rack rails. The adjustable mounting brackets installed in the rack ensure that the holes in the front-mounting brackets align with the holes in the rack rails.

    If the optional power cord tray is installed in a two-post rack, carefully slide the switch into the rack ensuring that the front bottom of the chassis rests on the lip of the power cord tray. The front-mounting brackets (ears) prevent the chassis from tipping too far back. Ensure that at least one person is supporting the rear of the chassis.

  6. Move the lift away from the rack.
  7. In the rack, push the bottom of the chassis so that the front-mounting bracket is flush with the front of the rack ensuring that one person continues to support the rear of the chassis.

    In a four-post rack, slide the chassis on the side rails of the adjustable mounting brackets, if installed, so that the front-mounting bracket is flush with the front of the rack.

  8. Install a mounting screw into each of the open front-mounting holes aligned with the rack, starting from the bottom.
  9. Visually inspect the alignment of the switch. If the switch is installed properly in the rack, all the mounting screws on one side of the rack are aligned with the mounting screws on the opposite side and the switch is level.
  10. After ensuring that the switch is aligned properly, tighten the screws.

Mounting an EX6210 Switch on a Rack or Cabinet Without Using a Mechanical Lift

If you cannot use a mechanical lift to install the switch, you can install it manually.

Caution

Lifting the chassis and mounting it in a rack or cabinet requires at least two people.

When lifting the chassis, do not grasp the switch by the panel at the top front of the chassis. Doing so can cause the panel to pop off of the switch.

Caution

Before front-mounting the switch in a rack, have a qualified technician verify that the rack is strong enough to support the switch's weight and is adequately supported at the installation site.

Before you install the switch:

  1. Prepare the site for installation as described in Site Preparation Checklist for an EX6210 Switch.
  2. Ensure the site has adequate clearance for both airflow and hardware maintenance as described in Clearance Requirements for Airflow and Hardware Maintenance for an EX6210 Switch.
  3. Unpack the switch as described in Unpacking an EX6200 Switch.
  4. Remove all components except the backplane from the chassis. See:
  5. In a two-post rack, you can install the optional power cord tray at the desired position (see Installing the Power Cord Tray in a Rack or Cabinet for an EX6200 Switch). The lip of the power cord tray will support the front of the chassis when you install the switch in the rack.

    In a four-post rack, install the optional adjustable mounting brackets at the desired position (see Installing Adjustable Mounting Brackets in a Rack or Cabinet for an EX6200 Switch). Optionally, you can also install the power cord tray and use it to manage the power supply cords.

  6. Review chassis lifting guidelines as described in Chassis and Component Lifting Guidelines.

Ensure that you have the following parts and tools available to install the switch:

  • 24 mounting screws appropriate for your rack

  • A Phillips (+) screwdriver, number 2 or number 3, depending on the size of your rack mounting screws

To install the switch in the rack or cabinet (see Figure 12 and Figure 13):

Caution

If you are installing more than one switch in a rack or cabinet, install the first one at the bottom of the rack.

  1. Ensure that the rack or cabinet is placed in its permanent location and is secured to the building.
  2. Position the switch in front of the rack or cabinet, centering it in front of the rack rails or the adjustable mounting brackets. Use a pallet jack if one is available.
  3. With one person on each side, hold the bottom of the chassis and carefully align the front mounting brackets of the switch with the rack rails at the desired location. See Figure 11.

    You can also lift the chassis onto the adjustable mounting brackets (if installed) in a four-post rack or onto the power cord tray (if installed) in a two-post rack and carefully align the front mounting brackets of the switch with the rack rails at the desired location.

    Warning

    To prevent injury, keep your back straight and lift with your legs, not your back. Do not twist your body as you lift. Balance the load evenly and be sure that your footing is firm.

    Figure 11: Lifting an EX6210 Switch Chassis Without Using a Mechanical Lift
    Lifting an EX6210 Switch
Chassis Without Using a Mechanical Lift
  4. Push the bottom of the chassis so that the front-mounting brackets are flush with the front of the rack. Ensure that one person supports the rear of the chassis while it is pushed in the rack.

    In a four-post rack, carefully slide the switch onto the adjustable mounting brackets (if installed) until the front-mounting brackets attached to the chassis contact the rack rails. The adjustable mounting brackets ensure that the holes in the front-mounting brackets attached to the chassis align with the holes in the rack rails.

    In a two-post rack, carefully slide the switch over the lip of the power cord tray (if installed) and into the rack. Push the bottom of the chassis so that the front-mounting brackets are flush with the front of the rack. Ensure that one person supports the rear of the chassis while it is pushed in the rack.

  5. Install a mounting screw into each of the open front-mounting holes aligned with the rack, starting from the bottom.
  6. Visually inspect the alignment of the chassis. If the chassis is installed properly in the rack, all the mounting screws on one side of the rack are aligned with the mounting screws on the opposite side and the switch is level.
  7. After ensuring that the switch is aligned properly, tighten the screws.
Figure 12: Installing an EX6210 Switch in a Two-Post Rack
Installing an
EX6210 Switch in a Two-Post Rack
Figure 13: Installing an EX6210 Switch in a Four-Post Rack
Installing an
EX6210 Switch in a Four-Post Rack

After you install the mounting screws and securely bolt the chassis to the rack, reinstall the components in the chassis. See:

Register Products—Mandatory for Validating SLAs

Register all new Juniper Networks hardware products and changes to an existing installed product using the Juniper Networks website to activate your hardware replacement service-level agreements (SLAs).

Caution

Register product serial numbers on the Juniper Networks website and update the installation base data if there is any addition or change to the installation base or if the installation base is moved. Juniper Networks will not be held accountable for not meeting the hardware replacement service-level agreement for products that do not have registered serial numbers or accurate installation base data.

Register your product(s) at https://tools.juniper.net/svcreg/SRegSerialNum.jsp.

Update your installation base at https://www.juniper.net/customers/csc/management/updateinstallbase.jsp.