Overview of Installing the T4000 Router

 

You must proceed through the installation process in the following order:

  1. Review all safety guidelines and warnings for the router.Warning

    To avoid harm to yourself or the router as you install and maintain it, you must follow the safety procedures for working with Internet routers, as well as the guidelines and warnings for working with and near electrical equipment. However, providing an exhaustive set of guidelines for working with electrical equipment is beyond the scope of this documentation.

    See General Safety Guidelines and Warnings.

  2. Prepare the installation site for the router.

    See Overview of Preparing the Site for the T4000 Router.

  3. Unpack the router and verify the parts received.

    See Overview of Unpacking the T4000 Router.

  4. Install the mounting hardware. See:
  5. Install the router into the rack. See:
  6. Ground the router.

    See Connecting the T4000 Grounding Cable.

  7. Connect the router to external devices. See:
  8. Connect the power. See:
  9. Power on the router.

    See Powering On the T4000 Router.