Site Preparation Checklist for a QFX5100 Device
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for QFX5100 deviceinstallation.
Table 1: Site Preparation Checklist
Item or Task | For More Information | Performed By | Date |
---|---|---|---|
Architecture | |||
Determine whether the QFX5100 device will operate:
|
|
|
|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances. | Environmental Requirements and Specifications for a QFX5100 Device |
|
|
Power | |||
Measure the distance between external power sources and switch installation site. |
|
|
|
Calculate the power consumption and requirements. |
|
| |
Rack or Cabinet | |||
Verify that your rack or cabinet meets the minimum requirements for the installation of the switch. |
|
| |
Plan rack or cabinet location, including required space clearances. | Clearance Requirements for Airflow and Hardware Maintenance for a QFX5100 Device |
|
|
Secure the rack or cabinet to the floor and building structure. |
|
|
|
Cables | |||
Acquire cables and connectors:
|
|
| |
Plan the cable routing and management. |
|
|
|