Optical ILA Site Preparation Checklist
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for an optical ILA installation.
Table 1: Site Preparation Checklist
Item or Task | For More Information | Performed by | Date |
---|---|---|---|
Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed the optical ILA tolerances. |
|
| |
Power | |||
Measure the distance between external power sources and the optical ILA installation site. |
|
|
|
Calculate the power consumption and requirements. |
|
| |
Rack or Cabinet | |||
Verify that your rack or cabinet meets the minimum requirements for the installation of the optical ILA. |
|
| |
Plan rack or cabinet location, including required space clearances. | Optical ILA Clearance Requirements for Airflow and Hardware Maintenance |
|
|
Secure the rack or cabinet to the floor and building structure. |
|
|
|
Cables | |||
Acquire cables and connectors:
|
|
| |
Plan the cable routing and management. |
|
|
|