M40e Clearance Requirements for Airflow and Hardware Maintenance
When planning the installation site, you must allow sufficient clearance around the rack (see Figure 1):
- For the cooling system to function properly, the airflow
around the chassis must be unrestricted. M40e Cooling System Description depicts the airflow in
the router.
Note: If you mount the router in a cabinet, be sure that ventilation is sufficient to prevent overheating.
- For service personnel to remove and install hardware components, there must be adequate space at the front and back of the router. At least 24 in. (61 cm) is required both in front of and behind the router. NEBS GR-63 recommends that you allow at least 30 in. (72.6 cm) in front of the rack and 24 in. (61 cm) behind the rack.
Figure 1: M40e Chassis Dimensions and Clearance Requirements