Installing the SRX5800 Services Gateway Mounting Hardware in an Open-Frame Rack

Before installing the services gateway in an open-frame rack, install the large mounting shelf on the rack. The small mounting shelf is not needed.

If you are front-mounting the services gateway, also remove the center-mounting brackets located on each side of the chassis.

Table 29 specifies the holes in which you insert screws to install the mounting hardware in an open-frame rack (an X indicates a mounting hole location). The hole distances are relative to one of the standard “U” divisions on the rack. For reference, the bottom of all mounting shelves is at 0.04 in. (0.02 U) above a “U” division.

Table 29: Open-Frame Rack Mounting Hole Locations

Hole

Distance Above “U” Division

Large Shelf

30

17.26 in. (43.8 cm)

9.86 U

X

27

15.51 in. (39.4 cm)

8.86 U

X

24

13.76 in. (34.9 cm)

7.86 U

X

21

12.01 in. (30.5 cm)

6.86 U

X

18

10.26 in. (26.0 cm)

5.86 U

X

15

8.51 in. (21.6 cm)

4.86 U

X

12

6.76 in. (17.1 cm)

3.86 U

X

9

5.01 in. (12.7 cm)

2.86 U

X

6

3.26 in. (8.3 cm)

1.86 U

X

3

1.51 in. (3.8 cm)

0.86 U

X

2

0.88 in. (2.2 cm)

0.50 U

X

1

0.25 in. (0.6 cm)

0.14 U

 

To install the large mounting shelf (see Figure 29):

  1. On the rear of each rack rail, partially insert a mounting screw into the highest hole specified in Table 29 for the large shelf.
  2. Install the large shelf on the rack. Hang the shelf over the mounting screws using the keyhole slots located near the top of the large shelf flanges.
  3. Partially insert screws into the open holes in the ears of the large shelf.
  4. Tighten all the screws completely.

Figure 29: Installing the Mounting Hardware for an Open-Frame Rack

Installing the Mounting
Hardware for an Open-Frame Rack

After the mounting hardware is installed, proceed to Installing the SRX5800 Services Gateway Chassis in the Rack.