Site Preparation Checklist for the SRX1400 Services Gateway
The checklist in Table 29 summarizes the tasks you need to perform when preparing a site for SRX1400 Services Gateway installation.
Table 29: Site Preparation Checklist
Item or Task | For More Information ... | Performed By | Date |
---|---|---|---|
Verify that environmental factors such as temperature and humidity do not exceed services gateway tolerances. | |||
Select the type of rack or cabinet. | |||
Plan rack or cabinet location, including required space clearances. | Clearance Requirements for Airflow and Hardware Maintenance of the SRX1400 Services Gateway | ||
If a rack is used, secure rack to floor and building structure. | |||
Acquire cables and connectors. | Console Port Cable and Wire Specifications for the SRX1400 Services Gateway | ||
Locate sites for connection of system grounding. | SRX1400 Services Gateway Grounding Cable SpecificationSignal Loss in Multimode and Single-Mode Fiber-Optic Cable for the SRX1400 Services Gateway | ||
Measure distance between external power sources and services gateway installation site. | |||
Calculate the optical power budget and optical power margin. | Calculating the Power Budget for Fiber-Optic Cable for the SRX1400 Services Gateway Calculating the Power Margin for Fiber-Optic Cable for the SRX1400 Services Gateway |