The checklist in Table 14 summarizes the tasks you need to perform when preparing a site for router installation.

Table 14: Site Preparation Checklist

Item or Task

Performed By

Date

Notes

Verify that environmental factors such as temperature and humidity do not exceed router tolerances (see Router Environmental Tolerances).

     

Measure distance between external power sources and router installation site.

     

Select the type of rack.

     

Plan rack location, including required space clearances.

     

Secure rack to floor and building structure.

     

Acquire cables and connectors.

     

Locate sites for connection of system grounding.

     

Calculate power budget and power margin.

     