[ Contents] [ Prev] [ Next] [ Index] [ Report an Error]

Site Preparation Checklist

The checklist in Table 17 summarizes the tasks you need to perform when preparing a site for router installation.

Table 17: Site Preparation Checklist

Item or Task

For More Information

Performed By

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed router tolerances.

Router Environmental Specifications

  
Power

Measure distance between external power sources and router installation site.

DC Power, Connection, and Cable Specifications

  

Locate sites for connection of system grounding.

Chassis Grounding

  

Calculate the power consumption and requirements.

Router Power Requirements

  
Hardware Configuration

Choose the configuration.

Hardware Component Overview

  
Rack

Verify that your rack meets the minimum requirements for the installation of the router.

Rack Requirements

  

Plan rack location, including required space clearances.

Clearance Requirements for Airflow and Hardware Maintenance

Rack Size and Strength

  

If a rack is used, secure rack to floor and building structure.

Connection to Building Structure

  
Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.
  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

Calculating Power Budget for Fiber-Optic Cable

Calculating Power Margin for Fiber-Optic Cable

  

Plan the cable routing and management.

Maintaining PICs and PIC Cables

  

[ Contents] [ Prev] [ Next] [ Index] [ Report an Error]