Site Preparation Checklist for the SRX3600 Services Gateway
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for services gateway installation.
Table 1: Site Preparation Checklist
Item or Task | For More Information ... | Performed By | Date |
|---|---|---|---|
Verify that environmental factors such as temperature and humidity do not exceed services gateway tolerances. | |||
Select the type of cabinet or rack. | SRX3600 Services Gateway Cabinet Size and Clearance Requirements and SRX3600 Services Gateway Rack Size and Strength Requirements | ||
Plan rack or cabinet location, including required space clearances. | |||
If a rack is used, secure rack to floor and building structure. | Connecting the SRX3600 Services Gateway to the Building Structure | ||
Acquire cables and connectors. | |||
Locate sites for connection of system grounding. | |||
Measure distance between external power sources and services gateway installation site. | |||
Calculate the optical power budget and optical power margin. | Calculating the Power Budget for Fiber-Optic Cable for the SRX3600 Services Gateway and Calculating the Power Margin for Fiber-Optic Cable for the SRX3600 Services Gateway |