Technical Documentation

Overview of Installing the T640 Router in the Rack

Before installing the router in the rack, verify that the following tasks have been completed:

  1. Review the T640 Site Preparation Checklist to verify that all the tasks required to prepare the site for router installation have been completed.
  2. Read the safety information in T640 Chassis Lifting Guidelines and Safety Requirements, Warnings, and Guidelines for Installing the T640 Router.
  3. Remove the router from the shipping crate as described in Unpacking the T640 Router.
  4. Install the mounting hardware as described in Installing the T640 Mounting Hardware for an Open-Frame Rack or Installing the T640 Mounting Hardware for a Four-Post Rack or Cabinet.

Because of the router's size and weight—up to 565 lb (256.3 kg) depending on the configuration—we strongly recommend that you install the router using a mechanical lift, as described in Installing the T640 Router Using a Mechanical Lift. If you do not use a lift to install the router, refer to Installing the T640 Chassis in the Rack Manually for complete instructions to safely install the router. Without a mechanical lift, at least four people are needed to safely lift the chassis into the rack or cabinet.

Related Topics


Published: 2010-08-11