Clearance Requirements for Airflow and Hardware Maintenance of the SRX100 Services Gateway
When planning the installation site for the SRX100 Services Gateway, you need to allow sufficient clearance around the device.
When planning the installation site for the services gateway, consider the following:
- For the operating temperature of the services gateway to be optimal, the airflow around the chassis must be unrestricted.
- For service personnel to remove and install hardware components, there must be adequate space at the front and back of the device. Allow at least 24 in. (61 cm) both in front of and behind the device.
- If you are mounting the device in a rack with other equipment,
or if you are placing it on the desktop near other equipment, ensure
that the exhaust from other equipment does not blow into the intake
vents of the chassis.
Table 1 provides information on the clearance requirements for maintaining the optimum airflow and the distances for facilitating easy maintenance of the device.
Table 1: Clearance Requirements for the SRX100 Services Gateway
Location
Recommended Clearance
Requirement for Clearance
Front of the chassis
2.5 in. (6.35 cm)
Space for service personnel to remove and install hardware components
Rear of the chassis
2.5 in. (6.35 cm)
Space for service personnel to remove and install hardware components
Between front-mounting flange and rack or cabinet edge
2.5 in. (6.35 cm)
Space for cable management and organization
Between side of the chassis and any non-heat-producing surface such as a wall or cabinet side
2.5 in. (6.35 cm)
Space for the cooling system to function properly and to maintain unrestricted airflow around the chassis
Between side of the chassis and devices that have fans or blowers
0.4 in. (1 cm)
Space for the cooling system to function properly and to maintain unrestricted airflow around the chassis
![]() | Note: The air vents are provided on the sides of the chassis for the SRX100 Services Gateway. |


