M7i Router Site Preparation Checklist
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for router installation.
Table 1: Site Preparation Checklist
Item or Task | Performed By | Date | Notes |
|---|---|---|---|
Verify that environmental factors such as temperature and humidity do not exceed router tolerances. | |||
Measure distance between external power sources and router installation site. | |||
Select the type of rack. | |||
Plan rack location, including required space clearances. | |||
Secure rack to floor and building structure. | |||
Acquire cables and connectors. | |||
Locate sites for connection of system grounding. | |||
Calculate power budget and power margin. |