M40e Site Preparation Checklist

The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for router installation.

Table 1: Site Preparation Checklist

Item or Task

For More Information

Performed By

Date

Environment

Verify that environmental factors such as temperature and humidity do not exceed router tolerances.

M40e Router Environmental Specifications

  
Power

Measure distance between external power sources and router installation site.

M40e AC Power, Connection, and Power Cord Specifications

M40e DC Power, Connection, and Cable Specifications

  

Locate sites for connection of system grounding.

M40e Chassis Grounding Specifications

  

Calculate the power consumption and requirements.

M40e Router Power Requirements

  
Hardware Configuration

Choose the configuration.

  
Rack

Verify that your rack meets the minimum requirements for the installation of the router.

M40e Rack Size and Strength

  

Plan rack location, including required space clearances.

M40e Clearance Requirements for Airflow and Hardware Maintenance

  

If a rack is used, secure rack to floor and building structure.

M40e Connection to Building Structure

  
Cables

Acquire cables and connectors:

  • Determine the number of cables needed based on your planned configuration.
  • Review the maximum distance allowed for each cable. Choose the length of cable based on the distance between the hardware components being connected.

Calculating Power Budget for Fiber-Optic Cable for M Series, MX Series, and T Series Routers

Calculating Power Margin for Fiber-Optic Cable for M Series, MX Series, and T Series Routers

  

Plan the cable routing and management.

Maintaining M40e PICs and PIC Cables

  