[Contents] [Prev] [Next] [Index] [Report an Error]

Example: Configuring a CCC over Frame Relay Encapsulated Interface

Configure a full-duplex Layer 2 switching circuit cross-connect between Router A and Router C, using a Juniper Networks routing platform, Router B, as the virtual switch. See the topology in Figure 10.

Figure 10: Example Topology of a Switching Circuit Cross-Connect with Frame Relay CCC Encapsulation

Image g017012.gif

[edit]
interfaces {
so-1/0/0 {
encapsulation frame-relay-ccc;
unit 1 {
point-to-point;
eui-64 frame-relay-ccc;
dlci 600;
}
}
so-2/0/0 {
encapsulation frame-relay-ccc;
unit 2 {
point-to-point;
encapsulation frame-relay-ccc;
dlci 750;
}
}
}
protocols {
connections {
interface-switch router-a-router-c {
interface so-1/0/0.1;
interface so-2/0/0.2;
}
}
mpls {
interface all;
}
}

[Contents] [Prev] [Next] [Index] [Report an Error]