We recommend that you use a standard EIA distribution rack. See Equipment Rack Requirements for rack information.
Before installing the systems in a rack, consider the following guidelines:
![]() |
Caution: To maintain airflow requirements, a plenum must be installed above the E320 router before any piece of equipment (other than an E320 router) is installed above the router. This plenum is available from Juniper Networks. Plenums are not required when E320 routers are installed above one another because the router has a built-in plenum at the bottom. See Installation Guidelines and Requirements and Figure 34. |
![]() |
Note: An optional mounting kit is available for mid-chassis mounting. Contact your Juniper Networks sales representative for more information. |
Following your installation plan, use a tape measure and marking pen to measure and mark space on each equipment rack for each router component. For horizontal spacing follow Network Equipment Building System (NEBS) requirements. To maintain airflow requirements, a plenum must be installed above the E320 router before any piece of equipment (other than an E320 router) is installed above the router. If you choose not to install a plenum, be sure to include 2 U of space between the E320 router and the other component for proper exhaust. A plenum, however, is highly recommended.
To complete the installation of the router in a rack, you need:
![]() |
Warning: Do not use the cable management bracket as a handle to lift the E320 router. |
To install the router in the rack: