    show chassis fabric reachability

    Syntax

    show chassis fabric reachability<detail>

    Release Information

    Command introduced before Junos OS Release 11.4.

    Command introduced in Junos OS Release 12.1 for MX240, MX480, and MX960 routers.

    Command introduced in Junos OS Release 12.1X48R4 for PTX Series Packet Transport Switches.

    Description

    (M320, MX240, MX480, MX960, and T Series routers only) Display the current state of fabric destination reachability. Additionally, display the details of the automated actions taken by the system to stop blackholing and attempt healing, and the final resolution of the actions.

    Options

    none

    Display the state of fabric destination reachability for M320, MX240, MX480, MX960, T640, and T1600 routers, based on periodic reachability checks. Display the system's action phase sequences to stop blackholing and attempt healing, and the final resolution.

    detail

    (Optional) Display the details of the actions carried out by the system in the different action phases and the final resolution.

    Required Privilege Level

    view

    List of Sample Output

    show chassis fabric reachability
    show chassis fabric reachability detail
    show chassis fabric reachability (PTX5000 system)

    Output Fields

    The table lists the output fields for the show chassis fabric reachability command. Output fields are listed in the approximate order in which they appear.

    Table 1: show chassis fabric reachability Output Fields

    Field Name

    Field Description

    Level of Output

    Fabric reachability status

    Display the reachability status of the fabric.

    • Enabled destinations transitioned to unreachable, Fabric down action in progress—Some enabled destinations that were originally reachable have become unreachable. The system is trying to stop the fabric down condition and attempt healing.
    • Enabled destinations reachable—The enabled destinations are reachable.
    • Unreachable destinations healed—The unreachable destinations are healed and are reachable.
    • Unreachable destinations removed—The unreachable destinations are removed.
    • Unreachable destinations present—Unreachable destinations are present in the system.
    • Unreachable destinations present due to FPC restart disable configuration—Unreachable destinations are present as a result of user configuration set to disable FPC restart.

    All levels

    Unreachable destinations

    Number of FPCs that have unreachable destinations.

    All levels

    Detected on

    Date and time when unreachable destinations are detected.

    All levels

    Reason

    Reason for the destination turning unreachable.

    • Single FPC error—A single bad FPC is not reachable over the fabric.
    • Fabric plane error—Multiple FPCs are not able to forward traffic over the fabric planes.

    All levels

    Fabric reachability action

    Action taken to handle the unreachable destination.

    • Plane Action—The healing is attempted only for the fabric planes.
    • SIB Action—(PTX Series system only) The healing is attempted only for the SIBs.
    • Plane and FPC Action—The healing is attempted both for the fabric planes and the FPCs.
    • SIB and FPC Action—(PTX Series system only) The healing is attempted both for the SIBs and the FPCs.
    • FPC Action—The healing is attempted only for the bad FPCs.

    All levels

    Acting on

    Current action is being performed on:

    • Single FPC error—The current operation is for healing the single bad FPC.
    • Fabric Plane error—The current operation is for healing the fabric planes.

    All levels

    Initial phase

    Starting phase for the healing action.

    • Plane restart—The fabric planes are restarted.
    • SIB restart—(PTX Series system only) The SIBs are restarted.
    • Plane and FPC restart—Both the fabric planes and affected FPCs are restarted.
    • SIB and FPC restart—(PTX Series system only) SIBs and affected FPCs are restarted.

    All levels

    Current phase

    Current phase for the healing action.

    • Plane restart—The fabric planes are restarted.
    • SIB restart—(PTX Series system only) The SIBs are restarted.
    • Plane and FPC restart—Both the fabric planes and affected FPCs are restarted.
    • SIB and FPC restart—(PTX Series system only) Both the SIBs and affected FPCs are restarted.
    • FPC offline—The FPCs are turned offline because the previously mentioned healing processes have failed.

    All levels

    Action started

    Date and time when the system fabric down healing attempt is started.

    All levels

    Plane restart phase

    The status of the plane restart phase.

    • Completed—The plane restart phase is completed.
    • In progress—The plane restart phase is in progress.

    detail

    Phase started

    Date and time when the plane restart phase is started.

    detail

    Planes restarted

    List of plane numbers restarted by the system.

    detail

    Planes timed out

    List of plane numbers that have timed out waiting to be restarted by the system.

    detail

    Planes being offlined / onlined

    Planes that are turned offline or turned online by the system, with date and time.

    detail

    Phase completed

    Date and time when the plane restart phase is completed.

    detail

    Plane and FPC Restart Phase

    Status of the plane and FPC restart phase.

    • Completed—The plane and FPC restart phase is completed.
    • In progress—The plane and FPC restart phase is in progress.

    detail

    Phase started

    Date and time when the plane and FPC restart phase is started.

    detail

    FPC Offline Started

    Date and time when the FPC offline action is started.

    detail

    Offlined FPCs

    List of FPCs that are turned offline by the system.

    detail

    FPCs timed out

    List of FPCs that have timed out waiting to be turned offline by the system.

    detail

    FPC being offlined

    FPC that is being turned offline by the system, with date and time.

    detail

    FPC Offline completed

    Date and time when the FPC offline action is completed.

    detail

    Plane restarting started

    Date and time when the plane restart action is started.

    detail

    Planes restarted

    List of planes restarted by the system.

    detail

    Planes being offlined / onlined

    Planes that are currently being turned offline or turned online by the system, with date and time.

    detail

    Plane restarting completed

    Date and time when the plane restarting action is completed.

    detail

    FPC online started

    Date and time when FPC online action is started.

    detail

    Onlined FPCs

    List of FPCs that are turned online by the system.

    detail

    FPCs timed out

    FPCs that have timed out waiting to be turned online by the system.

    detail

    FPC being onlined

    FPC that is being turned online by the system, with date and time.

    detail

    FPC Online completed

    Date and time when the action of turning the FPCs online is completed.

    detail

    Phase Completed

    Date and time when the plane and FPC restart phase is completed.

    detail

    Phase started

    Date and time when the plane and FPC restart phase is started.

    detail

    FPC restart time

    Date and time when the FPC restart action is started.

    detail

    FPC restarted

    FPC that is restarted by the system, with date and time.

    detail

    Phase Completed

    Date and time when the plane and FPC restart phase is completed.

    detail

    FPC Offline Phase

    Status of the FPC offline phase.

    • Completed— The FPC offline phase is completed.
    • In progress—The FPC offline phase is currently in progress.

    detail

    Phase started

    Date and time when the FPC offline phase is started.

    detail

    FPC Offline started

    Date and time when the FPC offline action is started.

    detail

    Offlined FPCs

    List of FPCs turned offline by the system.

    detail

    FPCs timed out

    List of FPCs that have timed out waiting to be turned offline by the system.

    detail

    FPC being offlined

    FPC that is being turned offline by the system, with date and time.

    detail

    FPC Offline completed

    Date and time when the FPC offline action is completed.

    detail

    Phase Completed

    Date and time when the FPC offline phase is completed.

    detail

    Action Completed

    Date and time when the system fabric down healing attempt is completed.

    All levels

    Fabric reachability resolution

    Status after the healing actions are performed.

    • Unreachable destinations healed after phase name—The unreachable destinations are healed after the healing actions are performed. The phase name indicates the last healing phase.
    • Unreachable destinations removed by FPCs FPC number offline—The unreachable destinations are removed by turning the FPCs offline.
    • Unreachable destinations present on FPC/PFE FPC/PFE number—The unreachable destinations are present on the FPCs or Packet Forwarding Engines and need to be acted upon.

    All levels

    Sample Output

    show chassis fabric reachability

    user@host> show chassis fabric reachability
    Fabric reachability status: Unreachable destinations removed
    
    Fabric reachability detection:
        Unreachable destinations                : Present on 3 FPCs
            Detected on                         : 2010-11-22 15:19:45 PST
            Reason                              : Fabric plane error
    
    Fabric reachability action:
        Fabric reachability action              : FPC action
        Acting on                               : Fabric plane error
        Initial phase                           : Plane restart
        Current phase                           : FPC offline is completed
        Action started                          : 2010-11-22 15:08:05 PST
        Action completed                        : 2010-11-22 15:19:45 PST
    
    Fabric reachability resolution: Unreachable destinations removed by FPCs 2, 3, 5
     offline
    

    show chassis fabric reachability detail

    user@host> show chassis fabric reachability detail
    Fabric reachability status: Unreachable destinations removed
    Fabric reachability detection:
        Unreachable destinations                : Present on 3 FPCs
            Detected on                         : 2010-11-15 15:50:32 PST
            Reason                              : Fabric plane error
    
    Fabric reachability action:
        Fabric reachability action              : FPC action
        Acting on                               : Fabric plane error
        Initial phase                           : Plane restart
        Current phase                           : FPC offline is completed
        Action started                          : 2010-11-15 15:41:47 PST
            Plane restart phase                 : Completed
                Phase started                   : 2010-11-15 15:41:47 PST
                    Planes restarted            : 0, 1, 2, 3, 4, 0
                Phase completed                 : 2010-11-15 15:42:14 PST
            Plane and FPC Restart Phase         : Completed
                Phase started                   : 2010-11-15 15:45:52 PST
                    FPC Offline Started         : 2010-11-15 15:45:52 PST
                        Offlined FPCs           : 2, 3, 5, 7
                    FPC Offline completed       : 2010-11-15 15:45:52 PST
                    Plane restarting started    : 2010-11-15 15:45:52 PST
                        Planes restarted        : 0, 1, 2, 3, 4, 0
                    Plane restarting completed  : 2010-11-15 15:46:11 PST
                    FPC online started          : 2010-11-15 15:46:11 PST
                        Onlined FPCs            : 2, 3, 5, 7
                    FPC online completed        : 2010-11-15 15:46:50 PST
                Phase completed                 : 2010-11-15 15:46:50 PST
            FPC offline phase                   : Completed
                Phase started                   : 2010-11-15 15:50:32 PST
                    FPC offline started         : 2010-11-15 15:50:32 PST
                        Offlined FPCs           : 2, 3, 5
                    FPC offline completed       : 2010-11-15 15:50:32 PST
                Phase completed                 : 2010-11-15 15:50:32 PST
        Action completed                        : 2010-11-15 15:50:32 PST
    
    Fabric reachability resolution: Unreachable destinations removed by FPCs 2, 3, 5
     offline

    show chassis fabric reachability (PTX5000 system)

    user@host> show chassis fabric reachability
    Fabric reachability status: Enabled destinations transitioned to unreachable, Fabric down action in progress
    
    Fabric reachability detection:
        Unreachable destinations                : Present on 5 FPCs
            Detected on                         : 2012-11-14 15:53:00 PST
            Reason                              : Fabric plane error
    
    Fabric reachability action:
        Fabric reachability action              : SIB action
        Acting on                               : Fabric plane error
        Initial phase                           : SIB restart
        Current phase                           : SIB restart is in progress
        Action started                          : 2012-11-14 15:53:00 PST

    Published: 2014-01-19