To verify that you have successfully completed the integration procedure, verify that the state of the control planes, switching planes, and interfaces is correct.
![]() | Note: Before you can issue the verification commands, you must be running the Junos OS Release 9.6R2 and later. |
See Verifying the State of the Routing Matrix Control Plane.
See Verifying That the FPCs on the T1600 Router Are Detected and Online.
See Verifying the State of the Switching Planes in the Routing Matrix.
See Verifying the State of the Interfaces on a T1600 Router.