Mounting a QFX3008-I Interconnect Device on a Rack or Cabinet
Using a Mechanical Lift
The QFX3008-I Interconnect device ships installed with front-mounting
brackets and center-mounting brackets on the chassis for mounting
the device on a 19-in. equipment rack or cabinet. (The remainder
of this topic uses “rack” to mean “rack or cabinet.”)
The chassis also comes with mounting shelves and brackets to support
it in the rack.
Because of the chassis size and weight, we require using a mechanical
lift to install the device.
 | Caution:
Before mounting the device in a rack, have a qualified
technician verify that the rack is strong enough to support the device’s
weight and is adequately supported at the installation site. |
 | Note:
In a rack, the chassis occupies 21 U. You can mount two
devices on a 42 U rack provided that the racks meet the strength requirements
to support the combined weight of the devices. If you are mounting
two devices on a rack, mount the first device on the bottom of the
rack. |
Before mounting a QFX3008-I Interconnect device in a
rack:
- Verify that the site meets the requirements described
in Site Preparation Checklist for a QFX3008-I Interconnect Device.
- Place the rack in its permanent location, allowing adequate
clearance for airflow and maintenance, and secure it to the building
structure. SeeClearance Requirements for Airflow and Hardware Maintenance for a QFX3008-I Interconnect Device for detailed information.
- Read General Safety Guidelines and Warnings, with particular attention to Chassis Lifting Guidelines for a QFX3008-I Interconnect Device.
- Unpack the device as described in Unpacking a QFX3008-I Interconnect Device.
- In a four-post rack, install the mounting hardware at
the desired position as described in Installing QFX3008-I Interconnect Device Mounting Hardware on Four-Post Racks or Cabinets. In a two-post rack, install the mounting
hardware at the desired position as described in Installing QFX3008-I Interconnect Device Mounting Hardware on Two-Post Racks.
Before you begin, ensure that you have the following
parts and tools available to mount the device in a rack:
- A mechanical lift with a load capacity of at least 750
lb (341 kg). If you do not have a lift rated for 750 lb (341 kg),
you must remove all components from the chassis and use a lift rated
for at least 250 lb (114 kg). The weight of an empty QFX3008-I Interconnect
device and midplane is approximately 205 lb (93 kg).
- Phillips (+) screwdriver, number 2 or number 3, depending
on the size of your rack mounting screws, for mounting the device
in a rack (not provided)
- Mounting screws appropriate for your rack (not provided)
- Rear support anchors to secure the chassis to the four-post
mounting shelf and rear support bracket (provided)
 | Note:
Earlier versions of the four-post rack mounting hardware
did not require the rear support anchors. If your four-post rack mounting
hardware includes spacer bars and two shelves the rear support anchors
are not required. |
- Four screws, two UNC 1/4-20 (right side) screws and two
M6 (left side) screws, to secure the rear support anchors to the chassis
(provided)
To mount the QFX3008-I Interconnect device in a rack
using a mechanical lift (see Figure 1 and Figure 2):
- Load the device onto the lift, making sure it rests securely
on the lift platform.
- Using the lift, position the device in front of the rack,
centering it in front of the mounting shelves installed in the rack.
- Lift the chassis approximately 0.75 in. (1.9 cm) above
the surface of the mounting shelves. Position the chassis in the rack
as close as possible to resting on the support that the mounting shelves
provide.
- In a four-post rack, carefully slide the device onto the
mounting shelves until the front-mounting brackets (“ears”)
attached to the chassis contact the rack rails. The handles on the
side of the chassis can be used to help position the Interconnect
device in the rack.
In a two-post rack, carefully slide the device onto the mounting
shelves until the center-mounting brackets (“ears”) attached
to the chassis contact the rack rails. The handles on the side of
the chassis can be used to help position the QFX3008-I Interconnect
device in the rack.
Figure 1: Installing a QFX3008-I
Interconnect Device in a Four-Post Rack
- Move the lift away from the rack.
- Ensure the mounting brackets are flush with the front
of the rack.
- Install a mounting screw into each of the open front-mounting
holes aligned with the rack, starting from the bottom.
- Visually inspect the alignment of the device. If the device
is installed properly in the rack, all the mounting screws on one
side of the rack are aligned with the mounting screws on the opposite
side, and the device is level.
- After ensuring that the device is aligned properly, tighten
the screws.
- In a four-post rack, hook the rear support anchors around
the bottom rear flange of the mounting shelf so that its holes line
up with the grounding lug screw holes at the bottom left and right
corner of the chassis rear.
 | Note:
Earlier versions of the four-post rack mounting hardware
did not require the rear support anchors. If your four-post rack mounting
hardware includes spacer bars and two shelves the rear support anchors
are not required. |
- Secure the rear support anchors with the provided UNC
1/4-20 (right side) screws and M6 (left side) screws.
Figure 2: Attaching Rear
Support Anchors to the QFX3008-I Chassis in a Four-Post Rack
Published: 2012-04-16