The checklist in Table 1 summarizes the tasks you need to perform to prepare a site for installing an EX8200 switch.
Table 1: Site Preparation Checklist
Item or Task
For More Information
Performed By
Date
Verify that environmental factors such as temperature and humidity do not exceed switch tolerances.
Environmental Requirements and Specifications for EX Series Switches
Measure distance between external power sources and switch installation site.
Calculate the power consumption and requirements.
AC Power Specifications for EX8200 Switches
DC Power Specifications for EX8200 Switches
Power Requirements for EX8208 Switch Components
Power Requirements for EX8216 Switch Components
Calculating Power Requirements for an EX8208 Switch
Calculating Power Requirements for an EX8216 Switch
Calculating the EX8200 Switch Fiber-Optic Cable Power Budget
Calculating the EX8200 Switch Fiber-Optic Cable Power Margin
Select the type of rack or cabinet and verify that it meets the minimum requirements for the installation of the switch.
Rack Requirements for an EX8208 Switch
Rack Requirements for an EX8216 Switch
Cabinet Requirements and Specifications for an EX8208 Switch
Cabinet Requirements and Specifications for an EX8216 Switch
Plan rack or cabinet location, ensuring the required space clearances.
Clearance Requirements for Airflow and Hardware Maintenance for an EX8208 Switch
Clearance Requirements for Airflow and Hardware Maintenance for an EX8216 Switch
Secure the rack or cabinet to the floor and building structure.
Plan the cable routing and management.
Acquire cables and connectors: