The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for router installation.
Table 1: M120 Site Preparation Checklist
Item or Task |
Performed By |
Date |
Notes |
|---|---|---|---|
Verify that environmental factors such as temperature and humidity do not exceed router tolerances (see M120 Router Environmental Specifications). |
|||
Measure distance between external power sources and router installation site. |
|||
Select the type of rack or cabinet. |
|||
Plan rack or cabinet location, including required space clearances. |
|||
If a rack is used, secure rack to floor and building structure. |
|||
Acquire cables and connectors. |
|||
Locate sites for connection of system grounding. |
|||
Calculate power budget and power margin. |