Site Preparation Checklist for the JCS1200 Platform
The checklist in Table 1 summarizes the tasks you need to perform when preparing a site for platform installation.
Table 1: Site Preparation Checklist
Item or Task |
For More Information |
Performed By |
Date |
|---|---|---|---|
| Environment | |||
Verify that environmental factors such as temperature and humidity do not exceed platform tolerances. |
|||
| Power | |||
Locate sites for connection of system grounding. |
|||
Calculate the power consumption and requirements. |
|||
| Rack | |||
Verify that your rack meets the minimum requirements for the installation of the platform. |
|||
Plan rack location, including required space clearances. |
JCS1200 Clearance Requirements for Airflow and Hardware Maintenance |
||
If a rack is used, secure rack to floor and building structure. |
|||