Juniper Networks
Log in
|
How to Buy
|
Contact Us
|
United States (Change)
Choose Country
Close

Choose Country

North America

  • United States

Europe

  • Deutschland - Germany
  • España - Spain
  • France
  • Italia - Italy
  • Россия - Russia
  • United Kingdom

Asia Pacific

  • Asean Region (Vietnam, Indonesia, Singapore, Malaysia)
  • Australia
  • 中国 - China
  • India
  • 日本 - Japan
  • 대한민국 - Korea
  • 台灣 - Taiwan
Solutions
Products & Services
Company
Partners
Support
Education
Community
Security Intelligence Center

Technical Documentation

Download Software
Research a Problem Login required
Case Management Login required
Contract & Product Management Login required
Technical Documentation
Documentation Archive
Enterprise MIBs
File Format Help
Glossary
Portable Libraries
End-of-Life Products
Contact Support
Guidelines and Policies
Security Resources
Home > Support > Technical Documentation > JCS 1200 Platform > JCS 1200 Hardware > JCS1200 Rack Requirements
Print
Rate and give feedback:  Feedback Received. Thank You!
Rate and give feedback: 
Close
This document helped resolve my issue.  Yes No

Additional Comments

800 characters remaining

May we contact you if necessary?

Name:  
E-mail: 
Submitting...
 

Related Documentation

  • JCS 1200
  • JCS1200 Installation Summary
  • Site Preparation Checklist for the JCS1200 Platform
  • JCS1200 Platform Environmental Specifications
  • JCS1200 Clearance Requirements for Airflow and Hardware Maintenance
 

JCS1200 Rack Requirements

The router can be installed in a rack. Many types of racks are acceptable, including four-post (telco) racks and open-frame racks. An example of an open-frame rack appears in Figure 1. Table 1 summarizes rack requirements and specifications for the JCS1200 platform.

Table 1: JCS1200 Rack Requirements and Specifications

Rack Requirement

Guidelines

Rack type and mounting bracket hole spacing

Use a four-post rack or a two-post rack. You can mount the router on any four-post or two-post rack that provides bracket holes or hole patterns spaced at 1 U (1.75-in./4.44-cm) increments and that meets the size and strength requirements specified in this table.

A U is the standard rack unit defined in Cabinets, Racks, Panels, and Associated Equipment (document number EIA-310–D) published by the Electronics Industry Association (http://www.eia.org).

Rack size and strength

  • Ensure that the rack is a 19-in. rack as defined in Cabinets, Racks, Panels, and Associated Equipment (document number EIA-310–D) published by the Electronics Industry Association (http://www.eia.org).
  • Ensure that the rack is one of the following standard lengths:
    • 23.62 in. (600 mm)
    • 30.0 in. (762 mm)
    • 31.5 in. (800 mm)
  • The rack rails must be spaced widely enough to accommodate the JCS1200 chassis's external dimensions: 21 in. (53.34 cm) high, 25.64 in. (65.1 cm) deep, and 17.43 in. (44.3 cm) wide. The outer edges of the mounting brackets extend the width to 19 in. (48.3 cm). The spacing of rails and adjacent racks must also allow for the clearances around the router and rack that are specified in JCS1200 Clearance Requirements for Airflow and Hardware Maintenance.
  • The JCS1200 platform ships with the mounting brackets. For instructions about moving the mounting hardware, see Installing the JCS1200 Mounting Hardware for an Open-Frame Rack or Installing the JCS1200 Mounting Hardware for a Four-Post Rack or Cabinet.
  • The chassis height of 21 in. (53.34 cm) is approximately 20 U. A U is the standard rack unit defined in Cabinets, Racks, Panels, and Associated Equipment (document number EIA-310-D) published by the Electronics Industry Association. You can stack several routers in a cabinet that has sufficient usable vertical space.
  • The rack must be strong enough to support the weight of the fully configured platform, up to 350 lb (158.8 kg). If you stack two fully configured platforms in one rack, it must be capable of supporting about 878 lb (399.1 kg).
  • Ensure that the spacing of rails and adjacent racks allows for the proper clearance around the platform and rack as specified in JCS1200 Clearance Requirements for Airflow and Hardware Maintenance.

Rack connection to the building structure

  • Secure the rack to the building structure.
  • If earthquakes are a possibility in your geographical area, secure the rack to the floor.
  • Secure the rack to the ceiling brackets as well as wall or floor brackets for maximum stability.

Figure 1: Typical Open-Frame Rack

Typical Open-Frame Rack
 

Related Documentation

  • JCS 1200
  • JCS1200 Installation Summary
  • Site Preparation Checklist for the JCS1200 Platform
  • JCS1200 Platform Environmental Specifications
  • JCS1200 Clearance Requirements for Airflow and Hardware Maintenance
 

Published: 2011-12-15

 
  • About Juniper
  • The New Network
  • Investor Relations
  • Press Releases
  • Newsletters
  • Juniper Offices
  • Resources
  • How to Buy
  • Partner Locator
  • Image Library
  • Visio Templates
  • Security Center
  • Community
  • Forums
  • Blogs
  • Junos Central
  • Social Media
  • Support
  • Technical Documentation
  • Knowledge Base (KB)
  • Software Downloads
  • Product Licensing
  • Contact Support
Site Map / RSS Feeds / Careers / Accessibility / Feedback / Privacy & Policy / Legal Notices
Copyright© 1999-2012 Juniper Networks, Inc. All rights reserved.
Help
|
My Account
|
Log Out